Sewer rates: Inside Town limits – Residential
Minimum 2,000 gallons $28.00
Over 2,000 gallons $5.50 per thousand gallons
On Tuesday, December 1st 2009, the White Bluff Town Council approved a 1.2 million dollar project plan to rehabilitate the sewer lines in White Bluff. The much needed repairs will replace and/or rehabilitate sewer lines that in some cases date back to the 1960’s. The project plan calls for project funding through a Community Development Block Grant (CDBG) with the Town responsible for up to $200,000.00 (two hundred thousand dollars) of the total project cost. The Town portion of the initial phase will be paid with cash on hand. This project plan does not include a sewer rate increase.
Please note that this timeline is approximate and may be impacted by factors such as weather, delays in permit approvals, construction delays, etc.
Sewer Project Timeline
|
Date
|
Description
|
|
July 11
|
Advertise for Bids
|
|
Aug 1
|
Open Bids
|
|
Aug 15
|
Preconstruction Conference
|
|
Aug 22
|
Start Construction
|
|
Dec 20
|
Finish Construction
|
The timeline is designed to allow Phase 1 completion before the project paperwork for Phase 2 is filed in the January / February 2012 timeframe.