Sanitation Department
 
Sewer rates: Inside Town limits – Residential
Minimum 2,000 gallons                            $28.00
Over 2,000 gallons                                    $5.50 per thousand gallons
 
On Tuesday, December 1st 2009, the White Bluff Town Council approved a 1.2 million dollar project plan to rehabilitate the sewer lines in White Bluff. The much needed repairs will replace and/or rehabilitate sewer lines that in some cases date back to the 1960’s. The project plan calls for project funding through a Community Development Block Grant (CDBG) with the Town responsible for up to $200,000.00 (two hundred thousand dollars) of the total project cost. The Town portion of the initial phase will be paid with cash on hand. This project plan does not include a sewer rate increase.
 
Please note that this timeline is approximate and may be impacted by factors such as weather, delays in permit approvals, construction delays, etc.
 
Sewer Project Timeline
Date
Description
July 11
Advertise for Bids
Aug 1
Open Bids
Aug 15
Preconstruction Conference
Aug 22
Start Construction
Dec 20
Finish Construction
 
The timeline is designed to allow Phase 1 completion before the project paperwork for Phase 2 is filed in the January / February 2012 timeframe.
 

Refer back to this page for project updates.